PLC Setpoint Ramp Rate Calculator
Build a setpoint or output ramp in a PLC: from the ramp rate and the task time, find the increment to add each scan and the time the ramp takes.
- Increment = rate ÷ 60 × Ts = 5 ÷ 60 × 0.1 s = 0.008333
- Ramp time = |end − start| ÷ rate = 12 min
- Each scan: SP = SP ± increment, clamp at end value
Ramp Formulas
Ramp time = |end − start| ÷ ramp rate
Ramp rate is in engineering units per minute, Ts the fixed task time in seconds. Run the ramp in a cyclic task with a known interval; in a free running scan, multiply the rate by the measured cycle time instead.
Worked example
Ramping a temperature setpoint at 5 °C/min in a 100 ms task adds 0.00833 °C each scan; going from 20 to 80 °C takes 12 min (7200 scans).
Frequently Asked Questions
Why ramp a setpoint?
To avoid thermal shock, pressure surges or large controller outputs when the setpoint changes, and to follow product recipes.
Where should the ramp run?
In a fixed interval cyclic task, so the increment per execution gives a known rate.
How do I stop overshoot of the end value?
Limit the ramped value so it never passes the target, then set it exactly to the target.