Commissioning · Free Template

Factory Acceptance Test (FAT) Checklist: Control Panel and DCS / PLC Template

A 24 point factory acceptance test checklist for control panels and PLC or DCS systems, with acceptance criteria for every item and an automatic pass and fail count.

Excel (.xlsx)Printable PDFFilled exampleFree, no sign up

Download

  • How to Use sheet with steps
  • Template sheet, blank and ready
  • Example sheet, filled in
  • 10 built in formulas
  • A4 landscape print setup
  • Works in Excel, Google Sheets and LibreOffice

Preview of the Filled Example

This is the Example sheet from the download, so you can see exactly how the completed factory acceptance test (fat) checklist: control panel and dcs / plc looks.

ProjectBoiler 3 control system upgrade
ClientABC Process Industries Ltd
System / panelPLC panel CP 03 and 2 HMI stations
VendorXYZ Automation Pvt Ltd
PO numberPO/4501/2026
FAT date12 Oct 2026
LocationVendor works, Pune
FAT procedureFAT PROC 03 Rev 1

Test checklist

NoSectionCheck itemAcceptance criteriaResultRemarks
1DocumentationApproved drawings, I/O list and FAT procedure availableLatest revision on filePASS
2DocumentationBill of materials matches supplied hardwareMake, model and quantity matchPASS
3VisualPanel dimensions, colour, IP rating and nameplatesAs per approved GA drawingPASS
4VisualWiring neat, ferruled, colour coded, segregated (IS / non IS, AC / DC)No damage, loose strands or mixPASS
5VisualEarth bars (PE, IE / clean earth) and bondingSeparate bars, all doors bondedPASS
6PowerInsulation resistance of incoming power circuits≥ 1 MΩ at 500 V DCPASS
7PowerPower on; all supply voltages measuredWithin ± 5 % of nominalPASS
8PowerRedundant power supply changeoverNo interruption to controllersPASS
9HardwareControllers, I/O cards and network switches healthyNo diagnostic alarmsPASS
10I/O testAnalog inputs: 4, 12, 20 mA injected on every channelReading within ± 0.25 % of spanPASS
11I/O testAnalog outputs: 0, 50, 100 % from HMI measuredWithin ± 0.25 % of spanPASS
12I/O testDigital inputs: every channel toggledCorrect tag changes state on HMIPASS

… and 12 more rows in the download.

PASS:22  ·  FAIL:1  ·  Not applicable:1  ·  Not yet tested:0  ·  FAT status:FAIL
Advertisement

About the Factory Acceptance Test (FAT) Checklist: Control Panel and DCS / PLC

A factory acceptance test checks a control panel or automation system at the vendor's works before it is shipped. Faults found at FAT cost a fraction of what they cost on site. A structured checklist with acceptance criteria avoids arguments: both sides agree in advance what "working" means.

How to fill in this template

  1. Agree the FAT procedure and this checklist with the vendor before the test date. Add or remove rows to suit your system.
  2. Fill the project details and test each item in order, witnessed by the client.
  3. Select PASS, FAIL or NA for every row and write remarks for FAIL and NA items.
  4. Every FAIL becomes a punch item; retest and update the result once fixed.
  5. Sign the checklist when the FAT status shows PASS or the open items are agreed in the punch list.

What the formulas do

  • Counts of PASS, FAIL, NA and untested rows.
  • FAT status is FAIL if any row failed, CHECK while rows are untested, otherwise PASS.

Related tools

Advertisement

Frequently Asked Questions

What is the difference between FAT and SAT?

FAT is done at the vendor's factory before dispatch, usually with simulated field signals. SAT is done after installation at site with real field devices and utilities.

Who attends a FAT?

The vendor's test engineer and the client, often with a third party inspector for large projects.

Should every I/O channel be tested in FAT?

Yes, ideally 100 % of channels. Sampling saves time but faults on untested channels then appear during commissioning.

You May Also Like

Learn more on the blog

Cold loop and hot loop testing procedures

A practical guide on instrumentationblog.in that explains the procedure behind this template and how engineers apply it on real plants.

Read Full Article