Commissioning · Free Template

Commissioning Punch List Template

Track every outstanding defect from inspection, FAT, SAT and walkdowns in one list. The sheet counts open items by category and shows how long each one has been open.

Excel (.xlsx)Printable PDFFilled exampleFree, no sign up

Download

  • How to Use sheet with steps
  • Template sheet, blank and ready
  • Example sheet, filled in
  • 88 built in formulas
  • A4 landscape print setup
  • Works in Excel, Google Sheets and LibreOffice

Preview of the Filled Example

This is the Example sheet from the download, so you can see exactly how the completed commissioning punch list looks.

Project / systemBoiler 3 control system
AreaUtilities block
Last updated12 Oct 2026
Punch list ownerCommissioning lead

Punch items (A: must close before start up, B: before handover, C: can remain after handover)

SrPunch noTag / areaDescriptionCategoryRaised byRaised onResponsibleTarget dateStatusClosed onDays openRemarks
1P 001PDT 3105M20 gland on M25 entry, replace with M25 Ex d glandAQC28 Sep 2026Contractor05 Oct 2026Closed03 Oct 20265
2P 002CP 03AI 02 CH 7 to 12: no open circuit alarmAClient01 Oct 2026Vendor15 Oct 2026Open12
3P 003JB 11Spare cores not ferruledBQC02 Oct 2026Contractor20 Oct 2026Open11
4P 004FV 3101Valve tag plate missingCOperations05 Oct 2026Contractor30 Oct 2026Open8
5P 005HMI 2Historian tags not updatingAClient08 Oct 2026IT / Vendor14 Oct 2026Open5
Open category A:2  ·  Open category B:1  ·  Open category C:1  ·  Closed:1
Advertisement

About the Commissioning Punch List

A punch list collects every incomplete or defective item found during construction, inspection and testing. Clear categories decide what blocks start up, and a single owner per item keeps the list moving. It is one of the most used documents in the final weeks of any project.

How to fill in this template

  1. Give every defect a unique punch number and a clear description that anyone can act on.
  2. Set the category: A must be closed before start up, B before handover, C may stay open after handover.
  3. Assign one responsible party and a target date.
  4. When an item is fixed and verified, set Status to Closed and enter the closed date.
  5. Review the open counts at every commissioning meeting.

What the formulas do

  • Days open = (closed date or today) − raised date.
  • Open item counts by category use COUNTIFS on Category and Status.

Related tools

Advertisement

Frequently Asked Questions

What do punch list categories A, B and C mean?

A items stop start up or are safety related; B items must be closed before handover; C items are minor and may be closed after handover.

Who closes a punch item?

The responsible party fixes it and the person who raised it (or QA/QC) verifies and closes it.

How often should the punch list be reviewed?

Daily or weekly during commissioning, depending on the number of open category A items.

You May Also Like

Learn more on the blog

Instrument loop checking procedure

A practical guide on instrumentationblog.in that explains the procedure behind this template and how engineers apply it on real plants.

Read Full Article