Instrument Material Take Off (MTO) Template

A material take off for instrument bulk items: tubing, fittings, valves, brackets, glands and cable. Quantity per hook up times the number of hook ups, plus wastage, gives the order quantity.

Excel (.xlsx)Printable PDFFilled exampleFree, no sign up

Download

  • How to Use sheet with steps
  • Template sheet, blank and ready
  • Example sheet, filled in
  • 160 built in formulas
  • A4 landscape print setup
  • Works in Excel, Google Sheets and LibreOffice

Preview of the Filled Example

This is the Example sheet from the download, so you can see exactly how the completed instrument material take off (mto) looks.

ProjectBoiler 3 upgrade
RevisionA
Date12 Oct 2026
BasisHook up drawings Rev B

Material take off

SrItemSpecificationMaterialSizeUnitQty per hook upNo of hook upsTotal qtyWastage (%)Order qty
1Instrument tubeSeamless, ASTM A269, 0.035" wallSS 3161/2" ODm614841093
2Male connectorTwin ferrule, tube x NPT(M)SS 3161/2" x 1/2"no21428530
32 valve manifoldBlock and bleed, 6000 psiSS 3161/2" NPTno18808
43 valve manifoldIntegral, for DP transmitterSS 3161/2" NPTno16606
5Root valveNeedle valve, 6000 psiSS 3161/2" NPTno2612012
62" pipe standFloor mounted, with base plateGalvanised CS2" NBno11414014
7Cable glandDouble compression, Ex d / Ex eNickel plated brassM20no214281031
Advertisement

About the Instrument Material Take Off (MTO)

Instrument bulk materials are bought long before installation, from hook up drawings rather than finished installations. A clear MTO avoids both shortages that stop work on site and expensive surplus at the end of the project.

How to fill in this template

  1. List each bulk item once, with a full specification so the buyer can order without questions.
  2. Count the quantity used in one hook up of each type from the hook up drawing.
  3. Enter how many instruments use that hook up.
  4. Set a wastage percentage for cut items such as tube and cable.
  5. Order quantity rounds up automatically.

What the formulas do

  • Total = quantity per hook up × number of hook ups.
  • Order quantity = ROUNDUP(total × (1 + wastage % ÷ 100)).

Related tools

Advertisement

Frequently Asked Questions

What is an MTO in instrumentation?

A material take off: a list of all bulk materials needed for instrument installation, calculated from hook up drawings and quantities.

How much wastage should I add to tubing?

Typically 5 to 10 % for tube and cable; fittings and valves are usually ordered exactly or with a small spare.

Where do hook up quantities come from?

From the bill of materials on each standard hook up drawing.

You May Also Like

Learn more on the blog

Material take off guide: 7 essential MTO components

A practical guide on instrumentationblog.in that explains the procedure behind this template and how engineers apply it on real plants.

Read Full Article